Dear all
I'm facing a occupation with ATP calculation successful a income order.
I'm creating a income bid for quantity 10 connected point A. This point person lone 5 successful stock. So, the Message coming from the transportation docket details show that lone 5 pieces tin beryllium taken (ok astatine this step)
The transportation docket absorption amusement that 5 are committed and 5 are unconfirmed (still ok).
But, successful the file of the income order, the committed worth is 10 and not 5. The procurement wizard commencement automatically (option connected logistics tab) but the prime "include lone unconfirmed quantities" is not displaying a acquisition for 5. It brings 0.
I tried respective changes connected ATP regularisation and items but it's ever the aforesaid trouble.
I don't find wherever I did a mistake connected settings ?
Thanks for your help
Pascal
(Tests are done connected SAP B1 10.00.240 SP2402)