Synchronous Goods movements failing/missing for extended production integration.
We want to use the extended production integration with PMR. Our System is a S/4 HANA 2022 System with FPS 02.
We want to consume order specific staged parts in the psa with direct backflush which should be possible since release 1909 with the help of synchronous goods movements.
"If you are using direct goods movements, you can enter a backflush in Production and the system processes the confirmation without a consumption posting delivery. Backflush-related consumption using direct goods movements works for components staged using single-order staging or cross-order staging."
what we did:
We adjusted the Production Scheduling Profile in a way that synchronous movements are allowed:
(setting 2 = only GI should also be fine. also tested)
furtermore in general the setting is active in regards to erp interface
example (among many others)
After releasing the order,
triggering staging/creating a pmr,
creating staging tasks with RF/webdynrpo app staging
for production for order specific parts
(incl. Badi implemented for correct qty) and
confirming we want to use co11n for cornfirmation
with the result that the staged stock (with pmr reservation) is NOT consumed and
we are getting cogi entries
(!!) important: we recognized via slg1: among some ppf errors, system is somehow trying to create a delivery in the background with qty zero which seems
incorrectsince we want to post sychronous/direct