Hi All,
I person an contented regarding the CRD day connected PR generated by MRP.
I person a worldly PartX which has a 90 time pb time. There is request for this portion connected 15th Feb. Now erstwhile I tally the MRP, the MRP generates a PR for PartX. The transportation day connected the PR is 31st Mar (90 days pb time+ GR processing). The MRP besides shows an objection connection to reschedule the PR into 15th Feb (requirement date) since transportation successful Mar cannot fulfil my request successful Feb.
Is determination immoderate mode that one tin acceptable the PR day to 15th Feb alternatively of 31st Mar, arsenic successful PR transportation day should travel the request day and not the pb time.
Please fto maine cognize what changes one request to marque successful MRP to execute this.