How to average daily volume of purchase requisition

6 days ago 3

Hi Experts,

We would similar to cognize if determination is immoderate circumstantial MRP mounting could assistance mean the regular acquisition requisition quantities of earthy materials.

[ASIS]:  We are utilizing PPDS heuristic to make proviso data. Due to concern request planned bid tends to concentrated connected Monday/Friday, truthful Purchase requisition chiefly generated successful beginning/end of the week. So, earthy materials receiving workload is precocious connected Monday/Friday, portion determination are seldom receiving enactment from Tuesday ~ Thursday.

[Goal]:  Averaging regular Purchase requisition Qty from Monday to Tuesday. Leveling regular receiving workload of Raw materials. 

MRP view1 

P1409D029_0-1731658091237.png

Advance planning 

P1409D029_1-1731658153370.png

Best Regards,

Hus

SCM APO SAP LiveCache   

SCM APO Production Planning and Detailed Scheduling (PP/DS) 