Activity rate calculation

5 months ago 56

In Cocd A, Actual cost is zero in production cost-center XYZ where there is production during the month, so there is non-zero activity quantity.

The cost associated with production cost-center XYZ is recorded on a service cost-center ABC of Cocd B.

Now the question is, business for multiple reasons do not want to charge any cost on production cost-center XYZ and at the same time they want SAP to consider total cost on service cost-centre ABC and total quantity on production cost-centre XYZ while calculating activity rate on production cost-centre XYZ.

Is there any standard SAP solution for this requirement

Thanks

Kishore Jain

Read Entire Article