Hi,
May I inquire for assistance successful explaining wherefore the Call Date for the archetypal Call Object enactment was called erstwhile determination is simply a Call Horizon of 45 DAYS? The details of the Maintenance Plan are arsenic follows:
Maintenance Plan created and scheduled : 29.01.2024
Cycle Unit : 1000 HR
Call Horizon : 45 DAYS
Start Counter Reading : 75830 (counter speechmaking erstwhile Maintenance Plan was created)
First Planned Date : 28.05.2024
First Call Date : 17.03.2024
Scheduling indicator : 3 - Performance Based
What is the ground of the Call Date? Shouldn't it beryllium based connected the Call Horizon? Thank you