Hi everyone,
We are presently successful the process of implementing an S/4HANA Public Cloud.
I person an acquisition an contented with exceptions reporting. Hope you could assistance me.
Say for a worldly determination are PO lines with exceptions (e.g. Reschedule in, out, cancellations).
When you tally the app 'Schedule MRP Rescheduling Checks', the bid enactment exceptions look connected the list.
However, erstwhile you corroborate the aforesaid bid lines (via 'Manage Supplier Confirmation' app) without changing anything. And past moving again 'Schedule MRP Rescheduling Checks'. It volition vanish from the exceptions list.
Note that erstwhile you cheque Manage Material Coverage and MD04, it is inactive appearing arsenic exceptions.
Has anyone encountered this contented before?
We inactive privation to spot confirmed orders that has exceptions but each clip you confirmed an order, it gets excluded and the MRP constituent converts to ShpgNt.
Thank you,
Marc